The ultimate objective of nation building is peace and harmony for Bhutan and her people

– His Majesty The Druk Gyalpo

Gallery

Contacts

De-suung Headquarters, Metog Lam, Thimphu

info@desuung.org.bt

332572/332573/332574
Toll free: 1411

The opening ceremony of Tangsibi Water Project under Ura Gewog was graced by Bumthang Dzongdag accompanied by Lam Neten of Zhung Dratshang, Drangpon, Dzongrab, Gewog Thrizin, SP from RBP, representatives from RBA, De-suung office, MoWHS and Local Government.
Ura Gewog Water Project in Bumthang is being executed as RGoB- De-suung partnership and is one of the activities under water flagship program.
 
This water project will benefit about 52 households with present population of 360. The project comprises construction of one intake water reservoir, transmission length of 6347m, three numbers of Break-Pressure Tank and distribution length of 4353m. 23 household water tap stands will be constructed.
 
The project will be implemented by 45 De-suups, 2 RBA Personnel and 2 technical person. The projects was commenced on 25th July, 2021 and estimated to be completed in next three months.
After completion, the projects will be officially handed over to the Dzongkhag /Gewog/ community for ownership, Operation and Maintenance.
221747946_3949132368543259_3391756780243901279_n