National Service Water Project
Water Project status
Scheme | Drinking water | Irrigation | Integrated | Status |
Completed | 25 | 5 | 4 | 34 |
Ongoing | 2 | 4 | 0 | 6 |
Total | 27 | 9 | 4 | 40 |
Ongoing Projects
Sl No | Project site | Scheme | Launch Date | Benefecaries Households | Trenching Distance | Remarks |
1 | Zham, Minje, Lhuntse WF project | Irrigation | 28th August 2021 | 380 acres for 28HH | 5.5 km | Active |
2 | Chukarpo- Jomotshangkha | Irrigation | 7th Dec 2021 | 113 HH/384Acres | 6.5 km | Active |
3 | Gelephu Thromde, Sarpang | Drinking Water | 22-Apr-22 | 4276 HH | 13.28 km | Active |
4 | Depsi, Thimphu | Drinking | 25th June 22 | 334 plots, 9150 population | 6.8 km | Active |
5 | Sebjana Irrigation, Khamed Gasa | Irrigation | 13th Sep 22 | 58 HH (120 Acre) | 3.02 km | Active |
6 | Omshari, Pemathang SJ | Irrigation | 11th Nov 2022 | 446 HH, 922 Acres | 7.036 km | Active |
Completed Projects
Sl No | Project site | Scheme | Commencement Date | Project duration | Date of completion | Benefecaries Households | Trenching Distance | Remarks |
1 | Kamji, Chukha | Drinking water | 2nd Feb 2021 | 3 momths | 24th April 2021 | 11HH, 89 people | 9.05km | COMPLETED |
2 | Kalapang, Mongar | Drinking+Irrigation | 17th Dec 2020 | 3 months | 10th May 2021 | 1 BHU, 22HH, 135 people, 42 Acres | 4.5km | COMPLETED |
3 | Dhangdhung Tongsa | Drinking water | 2nd Jan 2021 | 3 months | 28th April 2021 | 57HH, 285 people | 6.1kms | COMPLETED |
4 | Kana Dagana | Drinking water | 13th Mar 2021 | 3 months | 28th May 2021 | 86HH, 895 people | 9.85km | COMPLETED |
5 | Naja, Paro | Drinking water | 21st Feb 2021 | 4 months | 21st June 2021 | 87HH, 728 people | 4.341 Km | COMPLETED |
Bemphu, Naja Paro (continuation of Naja Project) | Drinking water | 6th Oct 2021 | 2 months | 15th december 2021 | 14HH, 115 people | 1.4km | ||
6 | Samtengang Wangdi | Drinking water | 18th Mar 2021 | 3 months | 10th June 2021 | 2 schools, 970 people | 7.09km | COMPLETED |
7 | Telung Pemagsthel | Drinking water | 18th Mar 2021 | 3 moths | 2nd July 2021 | 85HH, 340 people | 7.77km | COMPLETED |
8 | Gomdhar, S/jongkhar | Drinking water | 26th April 2021 | 6 months | 23rd July 2021 | 36HH, 240 people | 4.2 km | COMPLETED |
9 | Khar P/gatshel | Drinking water | 26th April 2021 | 3 months | 25th July 2021 | 66HH, 219 people | 6.6km | COMPLETED |
10 | Tshaphel, Haa | Drinking water | 15th June 2021 | 3 months | 8th September 2021 | 17HH, 1 school, 510 people | 2.61km | COMPLETED |
11 | S/jongkhar Throm, LAP 4 | Drinking water | 7th June 2021 | 4 months | 8th September 2021 | 61 HH, 1 school, 1500 People | 1.2 Km | COMPLETED |
12 | Guma Punakha | Drinking water | 11th Nov 2020 | 3 months | 25th September 21 | 225HH, 1945 people | 13Km | COMPLETED |
13 | Ramina, Gasa | Drinking water | 27th June 21 | 2 months | 30th September 21 | 192 HH (960 people) | 1.86km | COMPLETED |
14 | Tareythang, Sarpang | Irrigation | 28th Mar. 2021 | 3 months | 29th September 21 | 8 HH/ 7.71 acres | 1.7km | COMPLETED |
15 | Gomphu , Zemgang | Drinking water | 2nd June 2021 | 5 months | 6th October 21 | 63HH, 347 people | 2.6km | COMPLETED |
16 | Tangsibi Bumthang | Drinking water + Dry water irrigation | 25th July 21 | 4 months | 6th November 2021 | 52HH , 360 people | 6.34km | COMPLETED |
17 | Shyenyer,Bumthang | Drinking water | 27th July 21 | 3.5 months | 3rd November 2021 | 43HH, 330 people | 6.6 km | COMPLETED |
18 | Kheni, Trashiyangtse | Drinking water | 28th July 21 | 5 months | 11th November 2021 | 140HH, 865 poeple | 9km | COMPLETED |
19 | Semjong Tsirang | Drinking+Irrigation | 25th Nov 2020 | 3 months | 26th November 21 | 72HH/ 210acres (571 people) | 1.19km | COMPLETED |
20 | Domakhey Punakha | Drinking water | 23rd July 21 | 4.5 months | 6th March 22 | 142HH, | 9km | COMPLETED |
21 | Lingtey, Sang-Ngagcholing, Samtse WF project | Irrigation | 4th September, 2021 | 5 months | 24th March 22 | 54 HH,113 acres | 2.2 Km | COMPLETED |
22 | Tsirang Patsheling | Drinking water | 22nd Nov 21 | 4 months | 4th April 2022 | 47HH, 263 people | 8.32km | COMPLETED |
23 | Tshaidhang, Zemgang | Drinking water | 11th November 2021 | 4 months | 22-Apr-22 | 68 HH, 1 school , 1 BHU, 450 poeple | 4.1km | COMPLETED |
24 | Gyelpozhing, Mongar | Drinking water | 2nd June 2021 | 8months | 24-Apr-22 | 532 HH, 3200 people | 9.17km | COMPLETED |
25 | Khammed,Jigmecholing Sarpang | Drniking water | 25th Dec 2021 | 3 months | 20th May 2022 | 143HH, 743 people | 7.887km | COMPLETED |
26 | Lhamozingkha, Dagana | Drinking water | 9th May 2021 | 6 months | 27th May 2022 | 500 HH, 3000 people | 7.7Km | COMPLETED |
27 | Udzorong , Tashigang | Drinking water | 24th June 21 | 6.5 months | 24th July 2022 | 442 HH (2210 people) | 36.136 km | COMPLETED |
28 | Wophu, Gasa | Drinking water | 24-Apr-22 | 2 months | 20th August 2022 | 197 HH(985people) | 1.45 Km | COMPLETED |
29 | Wooling, Orong, S/Jongkhar | Drinking Water | 4-Apr-22 | 5 months | 31st Aug 2022 | 80 HH (334 people) | 5.45km | COMPLETED |
30 | Wangringmu, Ramjar, Tashiyangtse | Irrigation | 12-Jan-22 | 6 months | 4th sep 2022 | 333HH/ 170 acres | 6.9km | COMPLETED |
31 | Gida-Jamdo Mewang , Thimphu | Drinking water | 27th Dec 2021 | 4 months | 14th September 2022 | 96HH, 919 people | 14.69km | COMPLETED |
32 | Langjaru, Sombaykha, Haa | Integrated | 2nd Jan 2022 | 6 months | 6th Nov 2022 | 12HH/190.35 acres | 4.5 Km | COMPLETED |
33 | Khangdari-Godari, Yangneer, Tashigang | Irrigation | 26th November 2021 | 6 months | 14th Nov 2022 | 154 HH, 136.54 acres | 2.54 km | COMPLETED |
34 | Rawadrang Manchu,Tomshang T/Yangtse | Irrigation | 15th July 2022 | 5.5 months | 14th January 2023 | 90 HH (180 Acre) | 4.5 km | COMPLETED |