National Service Water Project

National Service Water Project

water project patch png

Inspired by the Royal Address of His Majesty The King to the Nation on 12 September 2020, calling on our youth to engage meaningfully in the process of Nation building amidst the COVID-19 pandemic. One of the main ways highlighted during the Royal Address was the potential for the youth to develop water projects considering the importance of safe and reliable drinking water for the people and the nation as a whole.

Consequent to the Royal Address, two De-suung National Service water pilot projects in Guma, Punakha and Samjong, Tsirang were launched on 11th November and 25th November 2020 respectively and thereafter, many more projects in partnership with MoWHS and MoAF were launched. Inspired by the Royal Vision, thousands of De-suups volunteered in various water projects and shouldered their responsibilities diligently, and have shown what many of us would have thought impossible. The projects was also able to meaningfully engage De-suups, upskill them, instill value of volunteerism and to connect to the far flung communities.

Through these projects, De-suups gained valuable technical experience in the design, construction, and supervision of a fairly complex construction of water projects.

As we celebrate the success of De-suung National Service water project and set a legacy in the history of water sector, we also celebrate the capabilities and potential of our youth to undertake even more challenging projects in the country and build our nation despite all the limitations posed by the current COVID-19 pandemic.

Water Project status

SchemeDrinking waterIrrigationIntegrated Status
Completed309443
Ongoing1001
Total319444

 


Ongoing Projects

Project site Scheme Commencement Date Project duration Exp. Date of completion Beneficiaries Households Trenching Distance Remarks
Lhayul A & B, Chudzom, Sarpang
Drinking
18th Jan 2024
6 months
18th July 2024
156, BHU, School
22.1 Km
Active


Completed Projects

Sl No.Project siteSchemeCommencement DateProject durationDate of completionBeneficiaries HouseholdsTrenching DistanceRemarks
1Kamji, ChukhaDrinking water2nd Feb 20213 months24th April 202111HH, 89 people9.05kmCOMPLETED
2Kalapang, MongarDrinking+Irrigation17th Dec 20203 months10th May 20211 BHU, 22HH, 135 people, 42 Acres4.5kmCOMPLETED
3Dhangdhung TongsaDrinking water2nd Jan 20213 months28th April 202157HH, 285 people6.1kmsCOMPLETED
4Kana DaganaDrinking water13th Mar 20213 months28th May 202186HH, 895 people9.85kmCOMPLETED
5Naja,  ParoDrinking water21st Feb 20214 months21st June 202187HH, 728 people4.341 KmCOMPLETED
Bemphu, Naja Paro (continuation of Naja Project)Drinking water6th Oct 20212 months15th December 202114HH, 115 people1.4km
6Samtengang WangdiDrinking water18th Mar 20213 months10th June 20212 schools, 970 people7.09kmCOMPLETED
7Telung PemagsthelDrinking water18th Mar 20213 months2nd July 202185HH, 340 people7.77kmCOMPLETED
8Gomdhar, S/jongkharDrinking water26th April 20216 months23rd July 202136HH, 240 people4.2 kmCOMPLETED
9Khar  P/gatshelDrinking water26th April 20213 months25th July 202166HH, 219 people6.6kmCOMPLETED
10Tshaphel, HaaDrinking water15th June 20213 months8th September 202117HH, 1 school, 510 people2.61kmCOMPLETED
11S/jongkhar Throm, LAP 4Drinking water7th June 20214 months8th September 202161 HH, 1 school, 1500  People1.2 KmCOMPLETED
12Guma PunakhaDrinking water11th Nov 20203 months25th September 21225HH, 1945 people13KmCOMPLETED
13Ramina, GasaDrinking water27th June 212 months30th September 21192 HH (960 people)1.86kmCOMPLETED
14Tareythang, SarpangIrrigation28th Mar. 20213 months29th September 218 HH/ 7.71 acres1.7kmCOMPLETED
15Gomphu , ZemgangDrinking water2nd June 20215 months6th October 2163HH, 347 people2.6kmCOMPLETED
16Tangsibi BumthangDrinking water + Dry water irrigation25th July 214 months6th November  202152HH, 360 people6.34kmCOMPLETED
17Shyenyer, BumthangDrinking water27th July 213.5 months3rd November  202143HH, 330 people6.6 kmCOMPLETED
18Kheni, TrashiyangtseDrinking water28th July 215 months11th November 2021140HH, 865 people9kmCOMPLETED
19Semjong  TsirangDrinking+Irrigation25th Nov 20203 months26th November 2172HH/ 210acres (571 people)1.19kmCOMPLETED
20Domakhey PunakhaDrinking water23rd July 214.5 months6th March 22142HH,9kmCOMPLETED
21Lingtey, Sang-Ngagcholing, Samtse WF projectIrrigation4th September 20215 months24th March 2254 HH,113 acres2.2 KmCOMPLETED
22Tsirang PatshelingDrinking water22nd Nov 214 months4th April 202247HH, 263 people8.32kmCOMPLETED
23Tshaidhang, ZemgangDrinking water11th November 20214 months22-Apr-2268 HH, 1 school , 1 BHU, 450 poeple4.1kmCOMPLETED
24Gyelpozhing, MongarDrinking water2nd June 20218months24-Apr-22532 HH, 3200 people9.17kmCOMPLETED
25Khammed,Jigmecholing SarpangDrinking water25th Dec 20213 months20th May 2022143HH, 743 people7.887kmCOMPLETED
26Lhamozingkha, DaganaDrinking water9th  May 20216 months27th May 2022500 HH, 3000 people7.7KmCOMPLETED
27Udzorong, TashigangDrinking water24th June 216.5 months24th July 2022442 HH (2210 people)36.136 kmCOMPLETED
28Wophu, GasaDrinking water24-Apr-222 months20th August 2022197 HH(985people)1.45 KmCOMPLETED
29Wooling, Orong, S/JongkharDrinking Water04-Apr-225 months31st Aug 202280 HH (334 people)5.45kmCOMPLETED 
30Wangringmu, Ramjar, TashiyangtseIrrigation12-Jan-226 months4th Sep 2022333HH/ 170 acres6.9kmCOMPLETED
31Gida-Jamdo Mewang , ThimphuDrinking water27th Dec 20214 months14th September 202296HH, 919 people14.69kmCOMPLETED
32Langjaru, Sombaykha, HaaIntegrated2nd Jan 20226 months6th Nov 202212HH/190.35 acres4.5 KmCOMPLETED
33Khangdari-Godari, Yangneer, TashigangIrrigation26th November 20216 months14th Nov 2022154 HH, 136.54 acres2.54 kmCOMPLETED
34Rawadrang Manchu, Tomshang T/YangtseIrrigation15th July 20225.5 months14th January 202390 HH (180 Acre)4.5 kmCOMPLETED
35Chukarpo- JomotshangkhaIrrigation7th Dec 20216 months19th Feb 2023136 HH/428Acres5.3kmCOMPLETED
36Zham, Minje, Lhuntse WF projectIrrigation28th August 20216 months19th March 2023380 acres for 42HH5.5 KmCOMPLETED
37Depsi, ThimphuDrinking25th June 228(excluding weekends and hindrance)25th Feb 2023334 plots, 9150 population6.8 kmCOMPLETED
38Sebjana Irrigation, Khamed GasaIrrigation13th  Sep 225 monthsFeb-2358 HH (120 Acre)3.02 kmCOMPLETED
39Omshari, Pemathang SJIrrigation11th Nov 20227 (220 days)Jun-23446 HH, 922 Acres7.036 kmCOMPLETED
40Martshalla, Samdrupcholing, SJDrinking8th Feb 20235 months (exc. holidays)Jun-2375 HH, 350 people8.77 kmCOMPLETED
41Lhachutang, Phuntshopelri gewog, SamtseDrinking17th March 20234 months (exc. holidays)14th Dec 202385 HH, 477 people10.34 kmCOMPLETED
42Gelephu Thromde, SarpangDrinking22nd April 202218 Months23rd Dec 20234276 HH, 60000 people12.3 kmCOMPLETED
43Gyata/Buli RWSS, Chumey, BumthangDrinking28th Sep 20235 Months2nd May 202465 HH, 1 Dratshang5.3 kmCOMPLETED